C-Power II & III

Period:
-

The 2nd and 3rd phase of the C-Power project are the industrial phases following the 1st phase considered as a pilot phase.

 

 

Project Description

Phase 2 and 3 consist of 48 6M Repower turbines (24 in each concession sub-area), the installation of the Offshore Transformer Station (OTS) and the installation of the 2nd 150 kV export cable. The wind turbines are built on jacket foundations and are connected together and to the OTS by 33 kV cables.

 

 

Project Details

Year 2012 - 2013. C-Power II & III was built from the Rebo-terminal in Port Oostende.

  • storage of the tower elements
  • storage of the hubs and nacelles
  • storage of the blades
  • pre-assembly of the blades on the hub
  • installed at sea with installation vessel Neptune

 

 